Garage Conversion ADU in Henderson, NV: What It Costs and How Long It Takes
A garage conversion ADU in Henderson runs $45,000 – $130,000 and takes roughly 3 to 5 months from permits to final inspection. Most of that money goes into the things you can’t see once the walls go back up: a raised, insulated floor over the slab, new electrical service, HVAC, plumbing for a kitchenette or bath, and windows pulled from the existing garage wall. Call (888) 282-1693 and we’ll walk your specific garage and give you a written, line-item estimate before anyone touches a tool.
How a garage conversion actually gets built here, stage by stage

This isn’t a weekend flip job, and the sequence matters more than the finishes. Here’s the real order of events.
Stages 1 to 2: design, engineering, and permits (4 to 8 weeks). We measure the garage, confirm ceiling height and how the existing slab sits, and get the drawings done. Because so many Henderson garages sit on post-tension slabs, we scan or x-ray the floor before any cutting is even proposed. You decide the layout at this stage: studio versus one-bedroom, where the bath lands, whether you want a kitchenette. Nothing gets built until the city signs off.
Stage 3: demo and rough-in (2 to 3 weeks). Out comes the garage door and opener, any shelving, and whatever the previous owner bolted down. The new raised floor goes in over the slab with a vapor barrier, which keeps the finished floor from pulling desert-ground moisture. Then electrical rough-in, plumbing if there’s a bath, and HVAC. You’ll pick fixture locations and confirm outlet placement around now.
Stage 4: framing, insulation, drywall, and the envelope (3 to 4 weeks). The old garage door opening gets framed and closed with a window or a solid wall. In Henderson, insulation is the whole ballgame in August, so we spec it for the heat, not for a mild climate. Stucco patching goes outside to match the house.
Stage 5: finishes and final inspection (3 to 4 weeks). Flooring, paint, trim, bath tile, fixtures, and the final walkthrough with the inspector. You’ll make your last calls here on paint color and flooring material. This is also when the smoke and CO detectors, egress windows, and any separation requirements get signed off.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll actually make, and what each one costs you
A garage conversion is a stack of decisions, and a few of them swing the budget more than the rest.
- Raised floor versus slab-on-grade. A framed floor over the existing slab keeps the unit warmer in winter and gives you a place to run plumbing and electrical without trenching. It costs more up front and eats 4 to 6 inches of headroom. Pouring a new finished slab is cheaper but locks your plumbing routes to wherever you can trench.
- Full bath versus half bath versus kitchenette. A full bath with a walk-in shower is the single biggest cost driver. Delta and American Standard fixtures land in the middle of the range and hold up; Toto sits at the high end for a reason. A half bath or a sink-and-fridge kitchenette cuts the plumbing work roughly in half.
- Egress and windows. A bedroom needs a properly sized egress window, which means cutting the existing garage wall and framing it. That’s a real line item, not a trim detail.
- Separate HVAC versus tying into the house. A dedicated mini-split gives the tenant their own thermostat and keeps you from overloading the main system. Tying in is cheaper but only works if the existing unit has capacity to spare.
- Finishes. Luxury vinyl plank handles desert humidity swings and rental wear without drama. Tile in the bath, with a proper waterproofing membrane like Schluter behind it, is the choice that keeps a shower from leaking into the framing a few years in.
What a Garage Conversion ADU costs in Henderson, NV

Plan on $45,000 – $130,000 for a garage conversion ADU in Henderson, with most projects landing in the $60,000 – $90,000 band. The low end is a studio with a half bath and a mini-split. The high end is a full one-bedroom with a kitchenette, a full bath, upgraded finishes, and a garage door opening rebuilt into a window wall.
Here’s what pushes a job toward the top of that range:
- Plumbing distance. The farther the new bath sits from the house’s existing drain lines, the more concrete and trenching you’re paying for.
- Electrical service. Older panels near downtown may need an upgrade to carry a separate unit. That’s a permit-scope cost, not a materials cost.
- Slab condition and cable location. Post-tension cables in the wrong spot mean engineering, scanning, and careful rerouting.
- Ceiling height. A raised floor helps the unit but only if there’s headroom to spare.
- Finish grade. Standard LVP and builder fixtures versus tile floors, a tiled shower, and premium plumbing fixtures.
A written estimate from us lists every one of those lines separately, with the permit fees and the inspection schedule spelled out. What it won’t include, and what we tell you up front: furniture, appliances you buy yourself, and any landscaping or driveway work around the unit. That last category is where homeowners often pair this with Concrete Driveways & Concrete Work in Henderson, since losing the garage means rethinking where cars actually park.
See the difference
Before
After
Before
After
Before
AfterWhat Henderson homes specifically do to this job
Henderson was built on engineered ground, and that shapes this work more than anything else. Nearly every subdivision here was graded over caliche-hard desert soil and, in places, former gypsum and borax mining ground. That means foundations, retaining walls, and slab conditions get real scrutiny, not a glance. In Green Valley, Anthem, and Seven Hills, the housing stock is overwhelmingly 1990s and 2000s tract construction, much of it on post-tension slabs, so any conversion that has to cut the floor gets scanned or x-rayed for tensioned cables first. Cables can’t be cut without an engineer signing off, and it’s a permit reality specific to Southern Nevada.
The heat matters too. With summer highs routinely over 110°F, insulation and HVAC sizing aren’t optional upgrades, and stucco patch work cures differently here than in wet climates. Monsoon season down the McCullough Range foothills is the other half of the story, which is why we care about how the converted unit sheds water away from the house. If the project grows into something larger, it’s really part of a full Home Additions & ADU in Henderson scope, and we handle that too. We cover all of Henderson, including the 89002, 89052, 89009, and 89016 ZIP codes.
Serving Henderson, NV – Our Local Coverage Area
We serve Henderson and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked questions about a Garage Conversion ADU in Henderson

Expect 3 to 5 months from contract to final inspection, with permits alone taking 4 to 8 weeks. The construction itself is usually 8 to 11 weeks. Call (888) 282-1693 for a realistic schedule based on your garage and the current permit queue.
Yes. A garage conversion ADU requires building, electrical, plumbing, and mechanical permits, plus a final inspection before you can legally rent or occupy it. Skipping permits is the fastest way to a problem at resale. We pull the permits and manage the inspections as part of the job.
Sometimes, yes. A studio with a half bath or a kitchenette can often route plumbing through the raised floor and up the existing wall, avoiding a slab cut entirely. A full bath with a distant drain location usually can’t. We’ll tell you which side of that line your garage falls on during the estimate.
The range is $45,000 – $130,000, with most projects settling between $60,000 and $90,000. The variables are bath count, plumbing distance, electrical service capacity, and finish grade. Call (888) 282-1693 for a written line-item quote, free of charge.
Every Garage Conversion ADU we build is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right. That’s one of the longest workmanship guarantees in residential construction, and it’s in writing, not in a handshake.
Get a free estimate on your Garage Conversion ADU
Call (888) 282-1693 and we’ll schedule a free on-site estimate at your Henderson home. You’ll get a written, line-item quote with permits, inspection milestones, and finish allowances spelled out, so the number you see is the number you pay. If the project grows past the garage, our Home Additions & ADU team can carry it from foundation to finish line. Homeowners often pair the work with Asphalt Driveways & Resurfacing in Henderson once the cars need a new home.