New Detached ADU in Paradise: What It Costs and How Long It Takes
A new detached ADU in Paradise typically runs $45,000 to $130,000 and takes four to eight months from first drawing to final inspection, depending on size, site work and how much utility trenching the lot needs. That figure covers a fully permitted, self-contained unit with its own kitchen, bath and sleeping area. Call (888) 282-1693 for a free on-site estimate, and we’ll tell you what your specific lot can carry before you spend a dollar on plans.
How a Detached ADU Gets Built, Stage by Stage

The sequence below is how a detached unit actually unfolds on a Paradise lot. Every stage has a decision waiting for you, so we lay it out up front instead of surprising you in month two.
Stage 1: Site walk and feasibility (week 1)
We measure setbacks, check where the sewer lateral and water main run, and look at how the lot drains. You decide the footprint: a 500 square foot studio, a 750 square foot one-bedroom, or closer to 1,000 square feet for a two-bedroom. Most Paradise lots in the 89105 ZIP can carry a detached unit, but alley placement and existing block walls often set the real limit, not the code book.
Feasibility work here is rarely a formality. Paradise parcels are a mixed bag: some carry a mid-century tract house on a generous lot, others sit tight against a neighbor’s block wall or a shared driveway. We walk the lot with you and tell you plainly what fits.
Stage 2: Design and permit package (weeks 2 through 10)
Drafting, structural calcs and the permit submittal happen here. This is the longest stretch with the least visible progress, and it’s where projects stall when the drawings are thin. You’ll sign off on the floor plan, the exterior finish and the roof pitch before anything goes to the county. Plan review in this corridor can take several weeks, sometimes longer if the parcel touches a commercial overlay or a resort-adjacent zone.
Stage 3: Site prep and foundation (weeks 10 through 16)
Clearing, grading, trenching for utilities and pouring the slab or stem-wall foundation. On Paradise lots the trenching is usually the wildcard: older blocks in 89105 can hit clay soil that needs over-excavation and a proper base before the pour, and we don’t skip that step to save a week. You’ll decide whether the unit ties into the main house’s electrical panel or needs its own service.
Stage 4: Framing, rough-in, and the inspection run (weeks 16 through 28)
Framing, sheathing, roof, then the rough electrical, plumbing and HVAC walk-throughs before insulation. Inspections come in sequence; each one clears before the next trade moves. You’ll pick fixtures and finishes during this window so nothing sits waiting at the end.
Stage 5: Finishes, punch list, final inspection (weeks 28 through 34)
Drywall, cabinets, tile, paint, flooring, exterior trim, and the landscape repair where we trenched. Then the final inspection and a walkthrough with you, item by item. If a shower valve drips or a door sticks, it gets fixed before we hand over keys, and it’s covered under our 730-Day Done Right Promise.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape Your New Detached ADU
Most of the money sits in a handful of decisions you’ll make in the first month. Here’s the honest trade-off on each.
- Footprint and bedroom count. A studio keeps the budget near the bottom of the range. Adding a second bedroom and a full second bath pushes toward the top. Larger units rent higher but cost more per square foot in foundation and roof work.
- Foundation type. Slab-on-grade is the standard and the cheapest route. A stem-wall or raised floor costs more up front but makes future plumbing repairs far easier. On clay-heavy soil we sometimes recommend the stronger base regardless of budget.
- Roofing. Asphalt shingle from a brand like GAF or CertainTeed is the value pick and holds up well under intense sun. Standing-seam metal costs more and reflects heat better, which matters in a Paradise summer. Tile sits at the premium end and looks right next to older Mediterranean-style homes.
- Exterior siding. Fiber cement from James Hardie resists sun and heat cracking better than vinyl and takes paint cleanly. Vinyl is cheaper and lighter but fades faster in direct sun.
- HVAC. A ductless mini-split system is the sensible fit for a detached unit and lets each zone run independently. A conventional ducted system costs about the same but wastes energy cooling empty rooms.
- Kitchen and bath finishes. A compact kitchen with standard cabinets reads fine to a renter. Upgrading to semi-custom cabinetry, quartz counters and a Kohler fixture package adds cost but supports a higher rent and a faster resale conversation later.
What a New Detached ADU Costs in Paradise, NV

Expect $45,000 to $130,000 for a detached unit in Paradise, with the bulk of the spread coming from size, site conditions and finish level. A compact studio on a clean, flat lot lands near $45,000. A two-bedroom unit with upgraded finishes, its own electrical service and significant clay-soil foundation work pushes past $100,000 and can reach the top of the range.
Four things move the number the most:
- Unit size. Square footage drives framing, roof, foundation and finish costs in a near-straight line.
- Site work. Trenching distance from the main house, clay soil, and any need to remove a wall or tree all add line items.
- Utility tie-ins. Tapping the existing panel is cheaper than a new service. Longer sewer runs cost more.
- Finish grade. Standard cabinets and vinyl flooring versus semi-custom cabinetry and tile change the total noticeably.
A written estimate from us breaks out each of those lines. It includes permits pulled and inspections passed, the foundation, framing, roof, mechanical rough-ins, finishes, and cleanup. It doesn’t include furniture, landscaping beyond trench repair, or appliances unless you ask us to spec them in. Upfront pricing means the number you see is the number you pay, and we don’t issue change orders for work already on the page.
See the difference
Before
After
Before
After
Before
AfterWhat Paradise Lots and Buildings Do to This Job
Paradise is a strange mix of mid-century tract homes and apartments from the 1950s through the 1970s sitting alongside high-rise resorts near the Strip and Convention Center. That matters for an ADU because the residential blocks in 89105 often date from an era when backyards were graded by eye, not by laser, and lots frequently carry clay soil that needs extra foundation prep before a slab goes down. We’ve pulled up on plenty of properties where the ground looked flat until we trenched it.
The other local reality is heat and schedule. Extreme summer sun sets limits on concrete curing and roofing adhesive, so a slab poured in July gets worked around the calendar differently than one poured in November. And because this is a corridor where crew labor is always being pulled toward resort-adjacent commercial work, we lock our trade schedule early rather than hoping framers are free next week.
If your project grows beyond a standalone unit into site grading, driveway access, or a full addition, that’s part of our Home Additions & ADU in Paradise work, and homeowners often pair this with Concrete Driveways & Concrete Work in Paradise to give the unit its own parking pad. We cover the whole of Paradise, from the 89105 blocks out toward the neighboring edges of Winchester and Spring Valley.
Serving Paradise, NV – Our Local Coverage Area
We serve Paradise and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions About a New Detached ADU in Paradise

Four to eight months from first site walk to final inspection. Permit review eats several weeks of that, and site prep runs longer on lots with clay soil. Call (888) 282-1693 for a timeline built around your lot.
Yes. A detached unit requires a full building permit and separate inspections for electrical, plumbing and mechanical. We pull the permits, handle the submittals and see each inspection through, so you aren’t chasing the county on your own. Call (888) 282-1693 to start with a feasibility check.
Sometimes, yes, if the unit can tie into an existing sewer lateral and electrical panel without re-routing, which keeps cost near the low end of the range. Older Paradise properties often need some re-routing, and we price that in from the start rather than as a surprise. Call (888) 282-1693 for a quote on your layout.
$45,000 to $130,000 depending on size, site conditions and finish level. A studio on a flat lot sits near $45,000; a two-bedroom with upgraded finishes and clay-soil foundation work reaches the upper end. Call (888) 282-1693 for an exact written quote, free of charge.
Every project is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right. That covers workmanship on the framing, roof, mechanical rough-ins and finishes, and it’s written into your contract. Call (888) 282-1693 with any question about coverage.
Get a Free On-Site Estimate for Your New Detached ADU in Paradise
We’ll walk your lot, measure the setbacks, check the utilities and give you a written line-item estimate with a realistic schedule, all at no cost. Calls are answered by a live person 24/7, so you won’t land in voicemail. Planning a larger scope? Start with our Home Additions & ADU service, or add a finished approach with Paver Driveways in Paradise. Call (888) 282-1693 to schedule your free estimate.